2024 City of Elk Grove Surface Treatment Project (WPR024)

 

Location

City Wide

City or County Responsible for Project

City of Elk Grove

Category

Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.

Description

The City of Elk Grove’s pavement maintenance program consists of four main treatments. Slurry Seal, Micro-Surfacing, Cape Seal and full Overlay. The City’s main objective is to identify the correct treatment for each street to achieve pavement preservation, increase safety, and enhance public access while maintaining a cost-effective mythology. The City utilizes StreetSaver and a Decision Tree of treatments to begin the planning process, but all streets are reviewed in the field by City staff before the final treatment has been decided.
The City has divided the road network into 113 subzones. This allows the City plan treatments by subzone to help reduce project costs, while reducing the repeated impacts to neighborhoods. The City has 5-yr streets plan that is update annually. The City looks at each subzone to determine if the area needs to be moved within the current 5 yr streets plan or added to it. The deterioration curve with the StreetSaver program is a good place to start, but not all streets age the same.
The City’s approach to projects is to streamline the process. This allows for a reduction in soft costs and puts a higher percentage of the budget direct into the street. The City has brought more of the project responsibilities in-house. This creates a better sense of “ownership” by staff who have been with the project from scoping through bidding and all the way to construction close out. Staff can directly see how the decisions that were made putting the project together played out in the field.
For the 2024 Surface Treatment Project (WPR024) the following work was completed:
Over 2 million SF of Type I Slurry Seal
Over 2.1 million SF of Type II Slurry Seal
Over 2.1 million SF of Type II Micro-Surfacing
Over 1.1 million SF of Cape Seal
Over 34,000 SF of Overlay
Also included were 125 ADA ramp improvements and every street that was resurfaced received a new traffic striping.

The total cost for this project was approximately $10.3 million dollars. This project was delivered on time and within budget.

The City completes PCI inspection of residential streets every four years and arterial/collectors every other year. The City’s PCI is currently at 80. The City’s PCI has steadily increased from 68 in 2015, to our current 80. The City also has an additional annual crack seal project where a 7th of the City streets received crack seal as part of the preventative maintenance program.

Funding is a combination or RMRA and Local