20th Street Bike and Pedestrian Connection Project
Location
20th Street and Michigan Avenue
City or County Responsible for Project
City of Santa Monica
Category
Complete Streets Projects
Description
In the mid-1960s, the construction of the Santa Monica Freeway (I-10) divided Michigan Avenue and displaced over 1,500 residents in the Pico Neighborhood. The 20th Street Bike and Pedestrian Connection Project is a critical link that reconnects Michigan Avenue for pedestrians and cyclists over the I-10 Freeway. This project sets the stage for the final phase of Michigan Avenue Neighborhood Greenway Plan (approved by the Santa Monica City Council in 2014) that will ultimately link the greenway to the Bergamot Arts Center and Bergamot Expo Line train station.
The Michigan Avenue Neighborhood Greenway (MANGo) offers a safe and pleasant space for the community, promoting walking, biking, and social interaction. MANGo’s traffic calming features aim to reduce heavy traffic volumes and speeding while connecting important destinations like Santa Monica High School, Edison Learning Academy, Santa Monica College, and Virginia Avenue Park. It also links to key bike routes, including protected bike lanes on 17th Street and Stewart Street (under construction) and standard bike lanes on 14th and 11th Streets.
The 20th Street Bike and Pedestrian Connection Project is a 1/8 of a mile protected multi-use path that closes the most complicated segment of the greenway plan by zig-zagging from the south side of the I-10 20th Street off ramp, over the 20th Street I-10 overpass, and along the north side of I-10 on Caltrans right-of-way adjacent to Crossroads School at 21st Street. The project includes:
• A separated bicycle and pedestrian path between 19th Court and 20th Street
• A two-way protected bikeway on the 20th Street overcrossing, with a separate bike signal phase for bike crossings
• A bicycle and pedestrian path between 20th Street and 21st Street along the northern side of tI-10
• Pedestrian scale lighting throughout
• Landscaping and fencing
The project, with a total cost of over $2.4 million, was funded through various sources, including Caltrans Active Transportation Program (ATP) grants and development transportation impact fees. Its implementation involved navigating numerous complex engineering and bureaucratic challenges. Extensive coordination and consensus-building were necessary, particularly to address security concerns from the adjacent multi-family development and Crossroads School as the project right-of-way meanders between City-owned, Caltrans, and private properties. Additionally, the project required collaboration with public utility stakeholders to relocate utility poles and to underground a Caltrans drainage ditch.
The project was rooted in foundational city initiatives ingrained in deep community engagement and feedback including the adopted Bike Action Plan Amendment, Pedestrian Action Plan, the Michigan Avenue Neighborhood Greenway (MANGo) Plan, and the city’s Land Use and Circulation Element. In addition to promoting sustainability and multi-modal transportation, the 20th Street Bike and Pedestrian Connection Project advances the city’s commitment to a Clean and Safe Santa Monica, including the Vision Zero initiative, which established the goal of eliminating severe traffic injuries and deaths on Santa Monica streets.
The 20th Street Bike and Pedestrian Connection Project has closed a critical and complicated gap in the Santa Monica bike network and Michigan Avenue Greenway. Moving forward, Santa Monica will build on this project’s success to complete the final phase of the MANGo plan to reconnect the Pico Neighborhood to the Bergamot E Line Station with a safe and seamless bike/pedestrian connection.
Project submitted by
Kyle Kozar
Principal Transportation Planner
Mobility Division, SaMoDOT