Bear Valley Road Reconstruction Project

 

Location

Amethyst Road to US Highway 395

City or County Responsible for Project

City of Victorville

Category

Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.

Description

Bear Valley Road is classified as a super arterial roadway on an east-west alignment that crosses the entire width of the City limits. As such, it experiences the highest-level of automobile traffic volume within the City, an average of 26,402 vehicles per day. Subsections of the road segment proposed for reconstruction and rehabilitation were constructed dating back to 1988. Over the past 35 years of service, some sections of pavement have been reconstructed, resurfaced, or widened as the City has developed.

As part of the City’s Capital Improvements Program, a two-mile stretch of roadway on Bear Valley Road was selected to be reconstructed. This segment included distresses such as: alligator cracking, shoving, potholes, raveling and rutting which indicate the asphalt and subgrade soils have reached their design life. Furthermore, in the Pavement Condition Index (PCI) survey conducted in 2022, this segment of road ranged from poor to fair. The last major rehabilitation surface treatment project for this segment was performed in 1996.

Due to the project’s proximity to utilities and US Highway 395, permits were required from multiple agencies including Los Angeles Department of Water and Power, Southern California Edison and California Department of Transportation. Close coordination with each entity was required to ensure the project’s success.

Bear Valley Road from Highway 395 to Amethyst Road was engineered in house to limit the scope of work where feasible and reduce construction costs. This value engineering included preserving existing road pavement sections that were less than 5 years old, resurfacing existing pavement sections that were less than 15 years old, and resurfacing sections of the center lane that experience little traffic. The remaining sections of the road experienced full depth, major reconstruction. All asphalt that was removed (approximately 83,000 square yards) was processed on-site and utilized as base for the new road section which was designed for Traffic Index of 13 as required per City Standard No. S-25; The new section is 6” of AC over 18” of base

Work along Bear Valley Road also included replacing existing concrete improvements that were damaged or non-ADA compliant, including curb and gutter, curb ramps, and drive approaches. New concrete curb and gutter and sidewalk adjacent to existing residential developments, and ADA compliant curb ramps at intersections where none existed, were also included. No road widening, new concrete sidewalk, curb and gutter or ramps were constructed adjacent to vacant undeveloped land as this will be the responsibility of the property owner/developer of the vacant land along the road.

The projected cost of the project was higher than the City’s annual SB-1 and Measure I (MSI) fund allocations. As a result, the City had to plan in advance and “save” funds from multiple years before moving forward with advertising the project.

In conclusion, the City’s sustainable pavement strategy applied in the Bear Valley Road Project enhanced the overall quality of the road network in a cost-efficient and eco-friendly manner. The three-pronged approach offers a proven solution for tackling challenges such as limited funding, value engineering, and resource conservation in a practical way. This project stands as a model and success story for other agencies aiming to adopt sustainable resurfacing and reconstruction methods.