Benton Way Pavement Rehabilitation Project
Location
Benton Way from Wetlands Edge Road to Elliott Drive
City or County Responsible for Project
City of American Canyon Public Works Engineering Division
Category
Complete Streets Projects
Description
The Benton Way Pavement Rehabilitation Project, designed and managed entirely by City staff, exemplifies how infrastructure improvements can transform a vital community corridor into a safer, more accessible space. This comprehensive project spans approximately 2,000 linear feet along Benton Way from Wetlands Edge Road to Elliot Drive, serving essential community facilities including American Canyon Middle School, Phillip West Aquatics Center and the Boys & Girls Club of Napa Valley.
The project addressed multiple critical needs through innovative design and implementation. The previously existing roadway, originally designed for a Traffic Index (TI) of 5.0 or less, was inadequate for current traffic demands. The roadway showed signs of alligator cracking, base failure and several trench cuts from previous utility repairs, resulting in a Pavement Condition Index of 45 (average). The rehabilitation utilized Full Depth Reclamation with Cement (FDR-C), an environmentally conscious approach that recycles existing pavement materials to create a new stabilized base, topped with 4-inch Hot Mix Asphalt, equipping the pavement to handle higher traffic demands (TI of 8).
The in-house design substantially enhanced safety and accessibility through installation of new curb extensions (bulb-outs) following Safe Routes to School recommendations, high-visibility crosswalks with enhanced striping, green-marked Class II bike lanes and Rectangular Rapid Flashing Beacons (RRFB) at uncontrolled crossings. The project also upgraded 17 curb ramps to ADA compliance and improved traffic-calming through strategic road width reduction.
City staff coordinated significant stakeholder collaboration, working closely with the school district, aquatic center and Boys & Girls Club to minimize disruption to operations. The City scheduled construction during summer break to reduce impacts on the school’s 1,075 students and 90 staff members, while maintaining access to the aquatic center’s 7,600 annual visitors and the clubhouse’s 200 youth program participants.
The $1.64 million project achieved cost-effectiveness through careful planning and execution by City staff, using a mix of funding sources: Measure T sales tax revenue, ARPA funds, SB1 RMRA and utility enterprise funds. The use of FDR-C technology provided substantial cost savings compared to traditional reconstruction methods and supported the City’s sustainability goals through material recycling.
The project has significantly improved community life, providing safer routes for students, enhanced accessibility for pedestrians and cyclists and upgraded infrastructure that will create a more livable, sustainable community for years to come. This project serves as a model for other communities, demonstrating how in-house expertise, collaborative planning and innovative engineering solutions can lead to comprehensive street improvements that enhance safety, accessibility and quality of life for residents and visitors alike.
Project submitted by
Kristine Delos Santos
Engineer III
City of American Canyon Public Works Engineering Division