Cañada Road Pavement Preservation Project
Location
Cañada Road in Unincorporated San Mateo County, CA
City or County Responsible for Project
County of San Mateo Department of Public Works
Category
Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.
Description
Cañada Road is a collector road located in the heart of San Mateo County (County) which spans 7.4 miles, renowned for its scenic mountain views and picturesque vistas of the lower Crystal Springs Reservoir. Connecting CA-92 in the north to the Town of Woodside in the south, it serves as an alternative route to I-280 and is a popular destination for cyclists seeking a scenic and recreational ride.
The Cañada Road Pavement Preservation Project (Project) scope of work included pavement repairs, micro-surfacing, striping, and new roadside traffic sign installation for the unincorporated section of Cañada Road which is approximately 5.5 miles in length. The Project has two main objectives, the first one being to preserve the existing pavement of Cañada Road, and the second is to improve roadway conditions for all users of the roadway that includes drivers, cyclist, and pedestrians.
The existing pavement of Cañada Road was in generally good condition with only minimal pavement repairs needed. Multiple road surface treatments for pavement preservation were evaluated by the County of San Mateo Department of Public Works (Department). The Department ultimately selected Type II micro-surfacing for its durability and ability to be applied at night, minimizing disruptions to the public.
The micro-surfacing was successfully completed in just four (4) nights under full road closures, compared to an estimated seven to eight days, if performed during the day with rolling lane closures. This approach significantly reduced traffic impacts, enhanced project efficiency, and conserved valuable resources for both the County and road users. In total, 140,000 square yards of micro-surfacing was applied, extending the roadway’s lifespan while ensuring a smooth and safe driving surface.
In addition to pavement preservation, the project improved roadway conditions through enhanced striping and lane modifications: Travel lanes were narrowed to 11 feet, allowing for the widening of bicycle lanes to 5 to 7 feet, improving cyclist comfort. Bike lane buffer zones were added where space permitted, further enhancing separation between vehicles and cyclists. 10.9 lane miles of bike lanes were improved, providing a safer and more accommodating experience for recreational and commuter cyclists. High-visibility crosswalks were installed at recreational trail crossings, complemented by advanced warning traffic signs to alert drivers and enhance pedestrian accessibility.
The Cañada Road Pavement Preservation Project was completed on time and within budget, demonstrating the County’s commitment to proactive infrastructure maintenance. The project was a high priority for the County and followed an accelerated design schedule. A design team completed it in six (6) months, integrating feedback from three community meetings, including a presentation to the County’s Bicycle and Pedestrian Advisory Committee. This participatory approach ensured the final design reflected the community’s input. By implementing an efficient, low-impact construction approach and prioritizing condition improvements, the Project successfully preserved the roadway while enhancing accessibility for all users.
This Project reflects the County’s dedication to maintaining its roadways in excellent condition, ensuring safe and enjoyable travel for residents and visitors alike.
Project submitted by
Leo Chow
Senior Civil Engineer
County of San Mateo Department of Public Works
555 County Center, 5th Floor, Redwood City, CA 94063
lchow@smcgov.org
650-363-4100