Castaic-Hasley Hills South

 

Location

Unincorporated Castaic

City or County Responsible for Project

Los Angeles County

Category

Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.

Description

Los Angeles County Public Works (Public Works) has utilized sustainable pavement treatments for street improvements with outstanding success and continues its commitment to preserving and improving the quality of its roads in a cost-effective and environmentally responsible way. California Mandate AB32, a state law requiring the reduction of greenhouse gas (GHG) emissions and a limited budget were the key motivators for developing our sustainable approach that emphasized (1) focusing on preserving roads in good conditions, (2) using recycled materials in pavement treatments, and (3) reutilizing materials in-place during construction. The Castaic–Hasley Hills South Project (Project), completed in August 2024, showcases the benefits of this sustainable approach. This project was funded with Road Maintenance and Rehabilitation Account (RMRA) funds.

The pavement conditions of nearly 5.8 centerline miles (1,000,000 square feet) of residential roads within the unincorporated Castaic area exhibited extensive moderate to severe distresses with subgrade failures for most of the streets in the community and were rated poor to fail. Reconstruction was considered the best solution to repair the roadways. The sustainable reconstruction approach of reutilizing the in-place materials, as opposed to traditional methods of removing and replacing materials, was estimated to save $3.5 million and achieved significant environmental benefits.

The County’s sustainable approach of cold central plant recycling (CCPR) and cement stabilized pulverized base (CSPB) was selected as part of the pavement treatment for this Project. The Project scope involved milling the existing asphalt and transporting it to an offsite location to be recycled, pulverizing and mixing cement with the remaining base and subgrade materials to provide a long-term structural section that would support the new road, processing the milled-off asphalt to be used as the asphalt base layer over the cement treated material, and finishing off with a new rubberized asphalt surface layer. The Project significantly shortened construction workdays and reduced traffic impacts. In addition to being cost-effective, this approach yielded significant environmental benefits. The CCPR and CSPB reduced energy consumption by 81 and 97 percent, GHG emissions by 83 and 96 percent respectively, and landfill use by nearly 135,000 cubic yards. Public Works reinvested the cost savings of $3.5 million to improve other County roadways.

In summary, the County’s sustainable pavement approach used in the Project improved the overall quality of Los Angeles County’s road network in a cost-effective and environmentally friendly way. The three-pronged approach is a proven formula for pragmatically addressing the issues of limited funding, reducing GHGs, and conserving resources. This Project is a model and success story for other agencies looking to implement sustainable resurfacing and reconstruction treatments.