Complete Streets: Downtown Burbank San Fernando Boulevard Reconfiguration, Phase 1

 

Location

San Fernando Boulevard, between Olive Avenue and Magnolia Boulevard

City or County Responsible for Project

Burbank, CA

Category

Complete Streets Projects

Description

Outstanding Local Streets and Roads Project Awards Program – City of Burbank
Downtown Burbank San Fernando Boulevard Reconfiguration, Phase 1 Project
• The entry directly improves the preservation, safety, access to, and overall quality of the local street and road system (up to 5 points)
The Downtown Burbank San Fernando Boulevard Reconfiguration, Phase 1 (Project), was designed with the express purpose of improving the safety, access, and overall quality of the local street and road system in Downtown Burbank. As a key component of Burbank’s Complete Our Streets Plan (adopted in 2020), the Project was implemented as a short-term priority to address the critical need for enhanced safety and multimodal access in one of the city’s most active corridors. The Project focused on a 12-month pilot reconfiguration of a three-block stretch of San Fernando Boulevard, which is not only the busiest in terms of both pedestrian and vehicular traffic but also serves as a commercial hub and regional destination. Data from the Complete Our Streets Plan highlighted this area’s high pedestrian and vehicular volumes, further emphasizing the need to reduce conflict points between road users. To achieve this, the Project removed one of the travel lanes, transforming the corridor from a two-way street to one northbound lane, effectively eliminating 50% of potential vehicle-pedestrian conflicts.
This lane reduction also presented new opportunities to improve the user experience for all roadway users. For motorists, the transition to a one-way configuration eliminated potential conflicts from oncoming traffic and illegal U-turns, which had been an ongoing issue in the corridor. The freed-up space from the removed lane was repurposed to create additional on-street short-term parking and commercial loading zones—key priorities identified by Downtown Burbank’s retail and business stakeholders. These changes addressed immediate needs for businesses while optimizing the limited street space for maximum benefit to the community.
For pedestrians, the reconfiguration allowed for the implementation of critical safety improvements, such as curb extensions made from quick-build materials like paint and plastic bollards. These enhancements shortened pedestrian crossing distances, improving safety and visibility for both pedestrians waiting to cross and drivers approaching crosswalks. Before the Project, yield compliance at unsignalized mid-block crosswalks in the Project Area was alarmingly low, hovering between 50% and 60%. After installation, yield compliance skyrocketed to above 80%, a clear indication of improved pedestrian safety. Furthermore, the narrow, one-way lane configuration helped reduce vehicle speeds, with the 85th percentile speed remaining consistent at approximately 20 mph—well below the posted speed limit of 25 mph—while providing a natural friction point that encouraged safer driving behavior.
• The entry is innovative and unique (up to 5 points)
The Project is a unique and innovative project that combines modern urban design with a holistic approach to mobility, sustainability, and community engagement. One of its most notable aspects is its seamless integration of multimodal transportation infrastructure, encouraging walking, biking, and sustainable transportation options while still maintaining vehicle access. This balance of different road users goes beyond traditional car-centric designs, reimagining how a downtown corridor can serve a wide range of needs. The project’s use of quick-build elements like plastic bollards, which can be easily replaced and recycled, demonstrates a commitment to sustainability without compromising functionality or long-term goals. In an urban environment where flexibility is key, these temporary structures allow for adjustments and experimentation, making it a forward-thinking example for future city designs.
Additionally, the project’s data-driven approach sets it apart. The City of Burbank collected comprehensive pre- and post-installation data to assess the effectiveness of the reconfiguration, analyzing metrics such as pedestrian safety, vehicle speeds, and commercial loading patterns. This focus on data not only informs the ongoing success of the project but provides valuable insights that can be shared with other cities looking to implement similar changes.
Two distinct features of the Project were its installation process, which lasted only four days and ensured minimal disruption to the community, and the use of “Sunshine Yellow” paint for all painted curb extensions, which in addition to enhancing the visibility of these pedestrianized areas, was picked to match the Downtown’s branding. Thereby serving a function of placemaking by elevating the aesthetic of Downtown while improving roadway safety.
While other cities have explored quick-build and multimodal street redesigns, the scale, integration of aesthetics, and level of community involvement in this project make it one of a kind. By combining cutting-edge design with sustainable materials, data-driven planning, and collaborative decision-making, it sets a new benchmark for urban transportation improvements that could inspire other cities in the region and beyond.
• The entry provides a model for others to follow (i.e. it is replicable) (up to 5 points)
The Downtown Burbank San Fernando Boulevard Reconfiguration serves as a replicable model for other jurisdictions looking to implement low-cost, quick-build projects that yield measurable safety benefits. As a 12-month pilot, the Project was designed to be easily installed and removed, making it an adaptable solution for cities that may want to test new designs without committing to permanent infrastructure changes. The Project relied on readily available, low-cost materials such as paint, plastic channelizers, traffic signs, minor signal modifications, and removable plastic planters. These materials allowed for a quick and cost-effective installation while still delivering significant safety improvements, such as enhanced pedestrian visibility, improved crosswalk compliance, and reduced vehicle speeds.
The City of Burbank led the design and installation process, with support from a design firm and a striping vendor who managed the installation of the modified striping, channelizers, and signage. Additionally, traffic signal reprogramming to accommodate the new one-way configuration was handled by City staff. This streamlined process, which involved a mix of in-house management and external contractors, ensures that similar projects can be implemented by other jurisdictions with varying levels of resources.
By utilizing temporary materials and strategies, the Project offers a low-risk, flexible framework that other cities and counties can easily replicate to improve safety and multimodal access on their own streets. The 12-month pilot approach ensures that jurisdictions can assess the impact of changes before making permanent alterations, thus making it a practical model for jurisdictions seeking cost-effective, scalable solutions.
• The entry’s positive outcomes are continuing/sustainable (up to 5 points)
Since its installation less than a year ago, the Project has delivered tangible and sustainable outcomes, earning strong support from City elected officials and community stakeholders. Following a six-month update where City staff highlighted its benefits, consensus among City decisionmakers and community stakeholders emerged to continue the pilot program. The Project has notably improved pedestrian safety by increasing yield compliance at three mid-block crosswalks in the Project Area. Utilizing quick-build materials has ensured low-cost maintenance, with the City prepared to address spot repairs and conduct regular cleaning. A key objective of this initiative is to demonstrate that quick-build projects can effectively test scalable roadway safety improvements. As the 12-month pilot concludes in March 2025, City leaders will evaluate the continued success of the Project across all user metrics to determine whether to advance to a second phase. This next phase would further enhance roadway safety and reimagine Downtown Burbank as a walkable, inviting destination through permanent improvements such as widened sidewalks, redesigned landscaped areas, additional outdoor dining spaces, new street furniture, and maintained vehicular access for businesses and merchants.
• The cost-effectiveness of the program/project (up to 5 points)
A key achievement of this Project was enhancing roadway safety for all users in a cost-effective manner. By utilizing affordable materials such as paint for striping, plastic K-71 bollards for traffic delineation, updated signage, removable planters, and minor traffic signal modifications, the Project successfully transformed a three-block stretch of Downtown Burbank. With a total cost of approximately $350,000—including design and installation—the Project remained within budget by leveraging a design and engineering firm for data collection, analysis, and striping plans while City staff managed overall implementation. Internal resources were used whenever possible, including developing the Traffic Control Plan, overseeing striping contractors, modifying traffic signals, and deploying changeable message screens.
Additionally, the Project’s low-cost, quick-build approach ensured that if the initiative had proven unsuccessful or if City decision-makers opted to modify or remove certain elements, adjustments could be made with minimal financial impact. Unlike permanent infrastructure projects, which require significant investments and extensive demolition to alter, the temporary nature of this installation allows for flexible refinements based on real-world feedback and evolving community needs. Ongoing maintenance costs are estimated at $100,000 to refresh striping, replace damaged bollards, and maintain planters. By delivering the Project on time and within budget, the City can now assess making these temporary roadway changes permanent while exploring similar low-cost quick-build solutions in other areas of Burbank.
• The entry has positive effects on the environment (up to 5 points)
By improving roadway safety, the Project has made Downtown Burbank more walkable for residents and visitors, encouraging active transportation and reducing dependence on cars. The reconfiguration of San Fernando Boulevard from one lane in each direction to a single northbound lane introduced a shared roadway with sharrow pavement markers, seamlessly integrating the Project Area into the City’s bicycle network. This expansion enhances bicycle connectivity across Burbank, allowing cyclists to travel more safely through Downtown while promoting a shift away from car reliance, thereby reducing vehicular emissions. Additionally, the Project introduced short-term commercial loading zones, enabling delivery and oversized vehicles to load and unload efficiently without excessive engine idling, further cutting down on air pollution.
Lower vehicular speeds were maintained throughout the corridor, and overall vehicle volumes slightly decreased, leading to reduced emissions and noise pollution, contributing to a quieter and cleaner urban environment. The Project also prioritized the use of sustainable materials with a lower carbon footprint. Instead of thermoplastics, which can degrade over time and contribute to water runoff pollution, the Project utilized paint, aligning with the temporary nature of the pilot.
Additionally, K-71 plastic bollards, used for traffic delineation, are recyclable and can be repurposed for future projects. To further enhance environmental benefits, the Project incorporated temporary self-watering planters with native plant species, reducing water consumption while beautifying the streetscape. Collectively, these measures demonstrate how the Project not only enhances mobility and safety but also promotes a more sustainable and environmentally responsible urban landscape.
• The entry demonstrates effective collaboration and partnerships ( 1 point)
This Project was guided from conception to implementation through strong collaboration and partnership. Extensive community outreach played a critical role, beginning with the development of the Burbank Complete Our Streets Plan—where the Project was first introduced—and continuing through community meetings with residents, businesses, and property owners during the design phase and installation process. City staff conducted multiple surveys of Downtown stakeholders to gauge interest and support, ensuring that diverse perspectives, needs, and priorities were considered. Given Downtown Burbank’s status as one of the City’s most economically vibrant areas, a key objective was to support and enhance economic activity while improving mobility and safety. The Downtown Burbank Property Business Improvement District Board played a vital role in this effort, working closely with City staff to convey merchant priorities and apply lessons learned from temporary roadway closures during the COVID-19 pandemic. This collaborative approach ensured that the Project maintained vehicular access while increasing on-street parking inventory and improving overall roadway safety.

Additionally, the Project benefited from strong internal coordination among multiple City departments, including Community Development, Public Works, Fire and Police Departments, Water and Power, and Parks and Recreation. Each department played an essential role in ensuring that the Project not only enhanced roadway safety but also preserved street operational capacity and maintained unimpeded access for emergency vehicles.

• The extent to which the results and benefits are publicly verifiable, measurable, replicable, and useful to other cities and counties (1 point)

The results and benefits of the Project are publicly verifiable, measurable, replicable, and useful to other cities and counties seeking to implement similar roadway safety improvements. The Project’s effectiveness is demonstrated through its adherence to safety countermeasures outlined in the Caltrans Local Roadway Safety Manual (2024), which provides clear crash reduction factors (CRF) for various interventions. By implementing proven countermeasures—such as converting San Fernando Boulevard to one-way operation (expected to reduce all collisions by 35%), adding delineators and object markers (CRF of 15%), installing curb extensions (expected to reduce pedestrian and bicycle collisions by 35%), and modifying traffic signals with Leading Pedestrian Intervals (expected to reduce pedestrian and bicycle collisions by 60%)—the Project’s safety benefits can be quantitatively assessed and verified.

To ensure a thorough evaluation, the Project’s success is measured through a robust set of metrics, with data collected both before and after installation to assess changes in key indicators. These include pedestrian and bicycle activity counts, safety analyses (vehicle speeds, yield compliance, and collision data), commercial loading activity monitoring, and traffic distribution studies. Pre-installation data, collected in 2022, established baseline conditions, while post-installation data gathered in May 2024 allowed for a direct comparison of outcomes. The results confirm measurable improvements in pedestrian safety, with crosswalk yield compliance increasing by more than 20% at key intersections, and by over 30% at others. Auto speeds remained largely unchanged, with 85% of vehicles traveling at or below 21 mph, ensuring a safe environment for all roadway users.

Beyond safety, the Project’s design supports commercial activity by maintaining vehicular access and expanding flexible loading and parking spaces. Analysis of commercial loading activity found that loading levels remained stable before and after installation, with increased utilization of designated spaces. From a mobility perspective, post-installation traffic analysis indicates that while vehicle volumes decreased on San Fernando Boulevard, pedestrian volumes remained high, with some areas experiencing increased foot traffic, demonstrating the corridor’s enhanced walkability. Bicycle activity remained steady, further supporting the Project’s role in promoting multimodal transportation. Traffic shifts to adjacent streets were observed, but intersection Level of Service (LOS) analysis found no significant delays, and any increase in vehicle queuing was attributed more to parking behavior than to the roadway reconfiguration itself.

In addition to quantitative data, the Project’s impact has been assessed through direct community feedback. A post-installation survey of Downtown businesses in July 2024 revealed that 54% of respondents agreed that the one-way configuration benefited the area, while 41% believed it helped attract more customers. Furthermore, 72% of respondents felt the current level of safety was appropriate, and 69% were either supportive or neutral about making the changes permanent.
• The extent technology is involved in innovative ways in the program/project (1 point)
The Project leveraged modern technologies and contemporary traffic engineering practices from design to implementation and in measuring its success. To effectively communicate the Project’s vision to stakeholders and decision-makers, Photoshop was used to create photo simulations illustrating how the changes would appear in the built environment. These visual materials helped convey the Project’s comprehensive nature, demonstrating how it would integrate seamlessly with Downtown Burbank’s existing aesthetic and enhance placemaking.
Advanced data collection technologies were also utilized to capture before-and-after conditions, ensuring an objective evaluation of the Project’s impacts. Radar sensors were deployed to measure vehicular volumes and speeds, while video recordings were conducted to assess curb and on-street parking utilization over time. Additionally, LiDAR and video analytics were employed to study near-miss collisions at high-pedestrian-volume intersections, providing critical insights into pedestrian safety improvements. Contemporary traffic engineering methods were applied to analyze traffic flow patterns and assess any shifts or unintended consequences resulting from the reconfiguration.
• The extent to which the program/project advances the League and CSAC’s priorities and goals for the local street and road system preservation (1 point)
The Project aligns with the League of California Cities (League) and the California State Association of Counties (CSAC) priorities by advancing roadway safety, multimodal accessibility, cost-effective infrastructure, and sustainability. A key goal of both organizations is to improve roadway safety while maintaining local street functionality. This Project supports that by implementing pedestrian and bicycle safety countermeasures from the Caltrans Local Roadway Safety Manual (2024), including curb extensions, leading pedestrian intervals, and enhanced crosswalks, reducing collisions and improving visibility. The data-driven approach shows measurable improvements, such as increased crosswalk yield compliance and fewer conflicts, ensuring streets prioritize safety without sacrificing mobility.
The Project also promotes cost-effective, sustainable infrastructure. By using quick-build materials like paint, plastic delineators, and removable planters, it achieved safety improvements at a fraction of traditional redesign costs. This low-cost approach allows the City to test changes before making permanent decisions, ensuring efficient use of public funds. Should modifications or removal be necessary, the temporary nature of the project minimizes financial losses.
In terms of multimodal accessibility, the Project improves pedestrian and bicycle connectivity, supporting the League and CSAC’s goal of promoting complete streets. The reconfiguration of San Fernando Boulevard into a one-way street introduced a shared, bicycle-friendly roadway, linking Downtown Burbank to the City’s broader bicycle network. The project’s enhancements, such as expanded crosswalk visibility and reduced crossing distances, make the area more pedestrian-friendly, encouraging non-motorized travel and reducing car dependency.
Sustainability is also a priority, with reduced vehicle speeds and slightly lower traffic volumes contributing to lower emissions and noise. The use of recyclable materials, like painted markings and reusable bollards, reduces the environmental footprint. Self-watering planters with native plants further enhance the streetscape while minimizing water use, demonstrating eco-friendly urban infrastructure.
Finally, the Project exemplifies the collaborative, data-driven planning advocated by the League and CSAC. Extensive community engagement balanced safety and accessibility with economic vitality, while modern data collection techniques, including LiDAR and radar monitoring, assessed traffic, pedestrian, and loading impacts, reflecting an innovative approach to local street preservation.
• Please identify if your project nomination was funded by the following. Check all that apply:
The Project was funded entirely through Measure R Local Return Funds.