Imperial Highway Corridor Capacity Enhancements Project

 

Location

Imperial Highway from Atlantic Avenue to the east City limit

City or County Responsible for Project

City of Lynwood

Category

Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.

Description

The Imperial Highway Corridor Capacity Enhancements Project represented a critical investment in traffic safety, congestion relief, and operational efficiency along one of the City of Lynwood’s most heavily traveled corridors. Delivered through a partnership between the City of Lynwood and the Los Angeles County Metropolitan Transportation Authority, the project was funded through Measure R grant funding and constructed at a total cost of $3,978,518.48.

The approximately 1 mile project extended along Imperial Highway from Atlantic Avenue to the east City limit, an area experiencing high traffic volumes due to its direct connection to the I 710 freeway. The corridor serves as a major regional route and required targeted improvements to enhance capacity, reduce conflicts, and improve overall safety for motorists and pedestrians.

The project included improvements at 11 coordinated signalized intersections, with 6 intersections receiving additional geometric enhancements. Work consisted of new asphalt concrete pavement, removal and reconstruction of existing pavement, raised medians, curbs, traffic signals, traffic detection loops, signing, striping, and landscaping. These improvements enhanced traffic flow, reduced delay, and improved intersection safety along the corridor.

Additional corridor enhancements included a grind and overlay of 0.5 miles of roadway, full depth pavement reconstruction at key locations, ornamental fencing and lighting rehabilitation, median curb installation, decorative landscaping, median irrigation improvements, and installation of a new City monument sign. Existing plastic channelizers along the centerline between Atlantic Avenue and St. James Street were replaced with new concrete curbs to improve durability and traffic safety.

During construction, City staff identified an opportunity to further enhance safety by extending the length of the landscaped median island between Atlantic Avenue and Wright Road. This modification reduced turning conflicts and improved traffic channelization along a high volume segment of the corridor. Due to traffic demands and freeway connectivity, paving activities were performed at night at several locations, including I 710 ramps, and lane closures were closely coordinated with Caltrans and its freeway construction contractor.

The completed project significantly improved corridor operations, safety, and aesthetics while demonstrating effective interagency coordination and cost effective delivery. The Imperial Highway Corridor Capacity Enhancements Project serves as a replicable model for cities seeking to implement targeted capacity and safety improvements on high volume arterial roadways connected to regional freeway systems.