Las Lomas Drive Bicycle Lane and Pedestrian Project

 

Location

Los Lomas Drive, from Hall Road to Thomas Road

City or County Responsible for Project

Monterey County

Category

Complete Streets Projects

Description

The Las Lomas Drive Bicycle Lane and Pedestrian Project improved the connectivity of the disadvantaged community of Las Lomas by improving safe access for bicyclists and pedestrians, especially students, complying with ADA requirements, providing air quality benefits that enhanced public health, and achieving greenhouse gas reduction by increasing biking and walking trips.
Initially, there were no sidewalks, shoulders, or bike lanes along Los Loma Drive, which caused unsafe conditions between vehicular users and pedestrians and bicyclists. The project widened the roadway to accommodate two 11-foot-wide travel lanes, added striping and signage, including a crosswalk at an intersection, and safer access to the only local market and other key destinations such as schools, bus stops, and community and employment centers. In addition to the widening, project features included driveway reconstruction, 1,320 linear feet of sidewalks, Class II bicycle lanes, curb, gutter, and sidewalk on the east side of the roadway, and a separated Class 1 pedestrian path on the west side, drainage inlets, a retaining wall, and Bio-infiltration ditches for Low Impact Development Features.
In compliance with the California Environmental Quality Act (CEQA), the Monterey County Planning Commission adopted a Subsequent Mitigated Negative Declaration and approved a Combined Development Permit. Caltrans approved the NEPA Categorical Exclusion Determination in January 2019 and re-validated said Determination in January 2023.
The County divided the project into two phases. Phase 1 provided drainage improvements on Las Lomas Drive, where the County constructed all the underground drainage features and acquired right of way for the project. Phase 2 was the roadway and bicycle lane improvement project, designed by TRC, who maintained ongoing coordination with the County and property owners from the Phase 1 project to ensure that the geometrics fit within the already acquired right of way. Complex geometry was required for the bio-infiltration system, as well as for the block retaining walls to stay within the right of way.
Construction activities required traffic control measures where traffic was stopped intermittently for the duration of the project, and a detour plan was distributed and posted. In addition, traffic control measures, such as lane closures and one lane reversible traffic control, were in place during active construction activities; traffic lanes were open during non-active construction activities.
Maintenance on the facility will be minimal since it will be newly constructed. As the pavement facility ages, routine maintenance will be required as normally performed by Public Works Maintenance.
The Project was funded by a combination of State and Federal ATP Funds, Transportation Development Act (TDA) funds and Measure X local funds.