McCourtney Road Rehabilitation Project
Location
McCourtney Road
City or County Responsible for Project
Nevada County
Category
Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.
Description
The County of Nevada’s 5-year Capital Improvement Program uses PCI (Pavement Condition Index) rating, ongoing maintenance activities and public input to determine how to best use our funds to increase our County wide PCI. This year’s annual roadway improvement project is part of a broader effort to improve how we address roadway conditions throughout the County. The McCourtney Road Rehabilitation Project, nick-named “Black Gold”, includes 3.2 miles roadway paving, shoulder widening, roadside drainage improvements, dig out and repair of poor asphalt, a 1.5” overlay, and placement of shoulder backing.
The Project was a collaborative effort between the County Road Department, the County Engineering Department and George Reed Construction.
The County Road Department milled 270 tons of damaged asphalt which was then screened and reused as shoulder backing on various County Roads. Additionally, the Road Department performed ~16,000 feet of roadside vegetation removal. The County engineers prepared the environmental document, plans and specifications, and provided construction management with George Reed Construction, to complete the project ahead of schedule and on budget.
The project rehabilitated a major roadway, that ties to the western county’s new transfer station. Project improvements include new drainage facilities, widening the roadway an average of 7’ to provide safer access to pedestrians and cyclists. Materials used in the project include use of 300 tons of recycled road grindings for shoulder backing and 5,000 tons of asphalt of which 580 tons was recycled materials.
To minimize impacts to the traveling public, notifications were made using multiple platforms. Changeable message boards were placed at either end of the project location, in advance of project construction, and throughout the project’s timeline. County’s website and social media posts were promulgated with information about the project. Staff at the McCourtney Road Transfer Station were frequently updated on the project should residents inquire about the project while at the facility. Coordination between the County and the transfer station was also done to prevent conflicts with their events, such as free green waste days, that generate higher than normal traffic in the area.
The project limits are from Larkspur lane to Patterson Valley Road. This $1.3M project was completed in 30 days and funded by Road Maintenance Recovery Account (SB1).
Project submitted by
Name
Patrick Perkins
Job Title
Principal Civil Engineer
Organization
Nevada County DPW
Address
950 Maidu Avenue
patrick.perkins@nevadacountyca.gov
Phone
5302651712