North McDowell Blvd. Complete Streets Project
Location
North McDowell Blvd. (from Old Redwood Highway to Sunrise Parkway)
City or County Responsible for Project
Petaluma
Category
Complete Streets Projects
Description
The City of Petaluma’s busiest arterial (over 20K vehicles daily) with the highest truck traffic (approaching 10%) is North McDowell Boulevard (NMD). Core business, industry, and residential hubs are located along the NMD project corridor. The Sonoma-Marin Area Rail Transit (SMART) track crosses NMD where the second Petaluma train station is under construction providing essential connectivity to the corridor and the community. Also, several transit bus lines run on NMD.
Unfortunately, the NMD pavement was 50+ years old and crumbling (PCI 7 to 38; very poor/poor classification); speeding was a leading contributor to the 132 injury collisions that occurred between 2016 and 2020; gaps in the sidewalk abounded along with non-ADA compliant curb ramps; transit facilities were inadequate without safe pedestrian crossings; and there were either none or limited bike facilities. The NMD Completed Streets Project (Project) required careful planning, public outreach, design, and construction for the efficient use of the limited funding available.
Funding for the project was a combination of local and state funds. Senate Bill 1 (SB1) provided initial money for the Project. Those funds were supplemented by Petaluma’s voter-backed 2020 Measure U sales tax bonds along with local street maintenance funding.
The NMD Complete Streets Project (Sunrise Parkway to Old Redwood Highway) has improved the roadway for the next 50 years to the accolades from the public. The project showcases the successful implementation of the California Complete Streets Act of 2008. The Complete Streets approach balances the needs of all users (pedestrians, cyclists, trucks, buses, rail and motor vehicles) to improve safety and equity on the busy corridor.
In addition to Complete Streets, the Project implements the City’s Vision Zero policy to eliminate all traffic fatalities and severe injuries (by 2030), while increasing safety, health, and, equitable mobility for all. The Vision Zero approach to the Project’s design included various means to slow traffic including lane narrowing, traffic signal timing, and corner bulb-outs. The other significant City policy put into place was Carbon Neutrality (by 2030). This policy is instigated with the City’s Climate Action Plan, a blueprint for the City’s Carbon Neutrality. This resulted in incorporating means to reduce and reuse project materials on the project, especially pavement recycling. The method used on this project was Cold Central Plant Recycling (CCPR), a rehabilitation process where materials are milled to the required depth, transported to a nearby cold central asphalt plant, processed, transported back to the road, and then laid with a paver.
Trees and/or turf landscaping needed to be removed in locations where sidewalk gaps were filled. To beautify the corridor overall and improve the tree canopy coverage, a treescape plan which includes many new tree plantings was developed for subsequent phases of the corridor improvements. This will help to ensure that those trees removed will be replaced with additional trees added. Areas with turf landscaping that had significant water usage were replaced with drought-tolerant landscaping to help conserve water in the future.
Bicyclist facilities were improved including direct connection with the SMART multi-use path and improved crossing of NMD (as part of the SMART improvements). Pylon-separated Class IV bike lanes were installed on over half the corridor with buffered and Class I facilities installed in other areas.
The Project’s construction entailed having to keep vehicular traffic flowing, especially for the businesses and the main USPS postal distribution facility for the region. The Project crossed the SMART railway tracks which necessitated careful coordination with the railway and traffic control execution.
The project was successfully completed at the end of 2023 with impactful safety improvements done in a sustainable manner that came under the projected budget. Now pedestrians can comfortably walk on both sides of NMD and cross it safely with lighted crosswalks and pedestrian refuge islands. Bicyclists have buffered bike lanes to travel in with green bike boxes at intersections to improve safety and city for users. Motor vehicle traffic has newly synchronized signals that will reduce backups and improve travel efficiency. The NMD Complete Streets project showcases the City’s ability to reconstruct the City’s busiest corridor for all users without adversely impacting vital business, traffic, active transportation, and transit operations. It is not easy to take a city’s busiest arterial and reconstruct it with a Complete Streets approach, but the City of Petaluma has successfully performed that important work!