Santa Cruz Coastal Rail Trail Segment 7
Location
Natural Bridges Dr to Pacific Ave/Santa Cruz Wharf and San Lorenzo Bridge; Santa Cruz, CA
City or County Responsible for Project
City of Santa Cruz
Category
Roads: Efficient and Sustainable Road Maintenance, Construction and Reconstruction Projects.
Description
The Santa Cruz Coastal Rail Trail Segment 7 Phase 2 represents a highly efficient and sustainable transportation infrastructure project that transformed a constrained rail corridor into a durable, low-stress multimodal route while addressing complex environmental and construction challenges. Led by the City of Santa Cruz, this project closed a critical 0.8-mile gap between Bay Street and Pacific Avenue, completing the final link needed to create a continuous bicycle and pedestrian connection from Natural Bridges to the San Lorenzo River and the broader regional trail network.
Segment 7 Phase 2 functions as a reconstructed transportation corridor that prioritizes long-term performance, safety, and climate resilience.
More than a recreational trail, it provides a reliable, car-free alternative for short trips to schools, employment centers, parks, and coastal destinations in an area where over 30,000 residents live within one mile of the corridor. By shifting these trips from vehicles to walking and biking, the project supports reduced roadway congestion, lower emissions, and long-term maintenance efficiencies consistent with sustainable roadway objectives.
The project required innovative design and construction solutions due to its narrow right-of-way between an active freight rail line and the Neary Lagoon Wildlife Refuge. To maximize usable width while minimizing environmental disturbance, the team designed a custom soldier pile retaining wall system that reduced grading impacts and provided a long-lasting structural solution tailored to site constraints. Drainage improvements, including subdrains and a French drain system, were integrated to address persistent groundwater and protect the trail from long-term moisture damage and erosion.
Construction efficiency was tested by unprecedented conditions. Work occurred during two consecutive winters of historic rainfall following prolonged drought, resulting in elevated groundwater and hillside seepage. The team adapted in real time, installing lean concrete backfill and enhanced drainage measures that were ultimately incorporated into the permanent design, strengthening the corridor’s resilience and reducing future maintenance needs. Additional challenges included unmarked utilities and limited access, which were addressed through close coordination, rail-mounted equipment, and precise construction sequencing.
Despite these challenges, the project maintained exceptional safety and environmental performance, achieving zero lost-time injuries and zero environmental incidents. Proactive soil management, biological monitoring, and daily safety protocols ensured protection of workers, the public, and adjacent natural resources.
Completed in May 2025, Santa Cruz Coastal Rail Trail Segment 7 Phase 2 demonstrates how thoughtful planning, adaptive construction management, and durable design can deliver sustainable transportation infrastructure under adverse conditions. The project sets a strong precedent for future corridor improvements and exemplifies efficient, resilient roadway and pathway reconstruction that serves both today’s users and long-term community goals.