The Skyway

The Skyway

Location: City of Chico – Town of Paradise
City or County Responsible for Project: Butte County
Award Category:
Roads: Efficient & Sustainable Road Reconstruction Project
Narrative Description of Your Entry:
For 72 years, the Skyway has served our mountain communities by providing an arterial connection to the State Highway System. Built in 1948 as a 2-lane road serving 2,400 vehicles per day, the Skyway today serves several communities and 12,000 vehicles per day, and is Butte County’s busiest roadway.
The Skyway provides a lifeline to services and an emergency evacuation route. On Nov 8, 2018, an electric transmission line ignited a firestorm known as the “Camp Fire,” one of the deadliest fires in California’s history. Shortly after the fire ignited, orders were given to evacuate the local communities, resulting in unprecedented traffic. The fire burned the Skyway, causing significant damage. During the long months of recovery work, the Skyway was further damaged by heavy industrial traffic, leaving it prematurely destroyed.
How does a local government replace such costly infrastructure? The process to fund/reconstruct a road involves years of planning. Congress authorized (in Title 23) the “Emergency Relief” (ER) program for the reconstruction of roads that have suffered catastrophic damage. The ER program is administered locally through Caltrans and provides federal reimbursement to local agencies, as funds are available.
The importance of the Skyway required the road be opened almost immediately. First however, the road had to be made safe enough for travel, which is referred to within the ER program as “Emergency Opening” (EO) efforts, along with a detailed damage assessment. Approximately 8 miles of 4-lane road would require mill/cold-plane to a depth of 0.25′, surfaced with 0.25′ (recycled content) hot mix asphalt, thermoplastic striping, and shoulder-backing. The cost to reconstruct the Skyway was estimated to exceed $17,000,000.00.
Normally, a construction project like this involves environmental studies and right-of-way (ROW). However, as a reconstruction project within the ER program, the work involved “replacement in kind” within existing ROW, allowing Caltrans to grant expedited approval of these phases. The reconstruction contract was awarded on April 12, 2022, for a bid amount of $10,580,073.00 (to Knife River Construction). Construction began shortly thereafter and the project was completed on October 12, 2022, at a final cost of $11,231,303.02.
Without the incredible help and guidance from our Office of Local Assistance (Caltrans District 3) AND funding made possible through the ER program, the Skyway reconstruction would not have been possible. Butte County is grateful for the ER Program and those at the State and Federal level that make reconstruction projects like this possible.